What aspects of Phases 2 and 3 are mandatory and which are optional?

In Phase 2, all the components are required except for the electrical/plumbing infrastructure for the future amphitheater improvements and the new access stairs to the LePort parking lot.  Per mandate of the county Fire Marshall, we are specifically required to complete the emergency vehicle turnaround before any other improvements can be done. We have an official, reciprocal  agreement with the LePort school to share our parking lots, and the current access stairs will not be accessible with the emergency vehicle turnaround installation. 

 

In Phase 3, all the components are required except the shade sails and the new AV kiosk and storage rooms.