What is the status of Phase 1 (Admin building overhaul)?

The permit for the repair and remodel of the Administration Building was issued in November 2023 and work started immediately. Target date for completion is June 2024. A contract for $281K was awarded to Chris Kolb for this project and will include a 193ft2 expansion for a new conference room; enclosed office for our DREF/Music Director; installation of a restroom and HVAC system; new walls, roofing, windows, and floor; stucco to match the rest of the buildings; and brush management improvements around the area.   This Phase is completely funded with the money available in our capital campaign fund.